HDD & Service Relocation Works
Completed HDD and civil works for the Heysen Tunnels Stage 2 project, including SAPN high voltage relocation, conduit installation, and excavation works, with zero safety or environmental incidents.

DTI engaged Bench Directional Drilling & Civil for drilling work as part of the Stage 2 Heysen Tunnels project, including service upgrades and rock drilling.
Works undertaken
- Successful installation of SAPN high voltage relocation via HDD and civil construction methodology
- Installation of 8 x E110mm conduits under the newly built Eagle on the Hill fire water tanks
- Excavation of joint bay in environmentally sensitive area completed
- Zero safety or environmental incidents